The evolution in the general political and financial environment in which ESA's Programmes are conducted has prompted the Agency's Member States to consider new forms of financial constraint for contributions to the Optional Programmes. The debate is well under way on the issue of national 'contributions' to ESA Optional Programmes outside the usual scheme of financial contributions provided for by the Convention, and it has already produced some interesting and innovative schemes. Also, the Council meeting at Ministerial Level on 4 March 1997 (reported in ESA Bulletin No. 89), in its Resolution on the Agency's industrial policy (Chapter III), indicated the need to examine these issues with a view to establishing rules applicable to 'In-Kind Deliveries' (IKDs).
Meteosat
In the Arrangement between the Member States and ESRO for
the Meteosat Programme in 1972, it was recognised that ESRO
would "make use of the result of the studies already covered
under the French national programme, and of certain facilities
and personnel of CNES". Detailed conditions were then agreed
in an ESRO/CNES Agreement. This formula was implemented by
ESRO (later by ESA) with a specific ESRO project team in
charge of the execution of the programme, based at the CNES
Toulouse Centre, and with CNES personnel made available free
of charge at the specific request of ESRO, plus functional
support. Contracts for carrying out the project were concluded
initially by ESRO and later by ESA.
Remote-Sensing Preparatory Programme
The Declaration on a Preparatory European Remote-Sensing
Satellite Programme provided that, for the purposes of the
programme: "Germany and France shall make available to the
Agency, free of charge, each within the area concerning it,
the results of studies and development work undertaken at
national level, identified by the Executive and recognised by
the Participants as being of direct interest to the
Preparatory Programme and of a value equal to, or greater
than, the difference between the 'direct costs' contributions
actually paid, and the contributions of the other
participants".
The Programme was actually carried out between 1979 and 1982 on this basis. This allowed both Germany and France to each contribute to external costs at a minimal level of 50000 AU whilst other participants were contributing substantially towards them but with provision for a guaranteed 100% geographical return.
Ariane
The Arrangement on the Ariane Programme signed in
September 1973 delegated programme management to CNES. This
Arrangement was accompanied by an ESRO/CNES Agreement, whereby
CNES was to provide a team (free of charge, except for mission
costs), place contracts and so on. This was followed by the
Resolution on the Ariane promotion series and the Declarations
on the following programmes based on Article V.1(b) of the
Convention, which were always supplemented by an ESA/CNES
Agreement. Much the same provisions are used for the Agency's
overall responsibility and CNES's technical and financial
management.
Hermes
The starting point was the Europeanisation of the
programme proposed by France involving a preparatory
programme, the development programme proper, a Declaration and
an ESA/CNES Agreement on the management scheme. Much the same
provisions were used for the respective roles of the Agency
and CNES, the arrangements for reporting technical
information, and in this case the setting-up of an
'integrated' team at the CNES Centre in Toulouse (F).
Envisat-1
Germany proposed that certain tasks included in the content of the POEM-1 Declaration, and included in the Envisat-1 Programme element funding, be funded by a special cash contribution from Germany on the explicit condition that contracts of the corresponding value be assigned to its national industry. These tasks are Ground Segment/Payload Data Segment items managed by ESA on behalf of Germany. Germany recognised that "the elements developed with this national funding are considered to be part of the Envisat Programme, and in particular part of the approved Ground Segment concept". This special German contribution amounts to approximately 5.5 MAU (including an element reserved for ESA management costs).
Risk factors, as well as management aspects, remain under the close scrutiny of ESA, in accordance with additional arrangements established between ESA and DARA. Considering these special circumstances, this Envisat case cannot merely be likened to the previous cases of national works contributed in-kind, but has to be regarded rather as a special financial contribution by Germany outside the criteria of the Programme Declaration and its envelope. This extra contribution has also been made in the spirit of easing the impact of the existing under-subscription of the financial envelope. In this respect, it does not have a direct parallel with earlier events and should not be confused with a typical in-kind delivery. In fact, the accepted documents explicitly mention that this 'special contribution offered by Germany remains outside the financial envelope'.
Artes-9
The Artes Programme participants have defined and have
subsequently subscribed to Element 9 of the Artes Programme,
covering works related to the GNSS (Global Satellite
Navigation System). The relevant Appendices A and B to the
Artes Declaration have inserted in the Programme the concept
of 'In-Kind Deliveries' (IKDs), funded nationally outside the
ESA programme framework, and put at the disposal of the ESA
programme through a grant in-kind and transfer of ownership.
The legal status of such an IKD is explained in the Artes-9
Implementing Rules, approved by Council on 20 July 1995. A
precise description of each of the agreed IKDs is added to the
Appendix B before being included in the programme's work
planning.
The Artes-9 Implementing Rules regulate in detail, within the General Implementing Rules of Artes, the special cases of in-kind deliveries and the related activities, including the administration and charging of ESA internal costs covering management and monitoring activities within the programme. This heavy regulatory exercise was necessary in order to incorporate this novel approach. In this case, important portions of the programme are intended to be contributed by Participating States, as in-kind deliveries, accompanied by some financial contribution to cover internal costs and other programme activities. Therefore, for the first time in an ESA Optional Programme and in a very new programme approach, a substantial part of a project consists of a coordination of national activities, or development works to be undertaken nationally, with a view to a European coherence for unified ultimate use and exploitation.
This list is not intended to be exhaustive, but is rather a series of examples chosen to illustrate past practice in ESA's Programmes and its evolution. Based on past experience and accepted practice, the following should not be considered as national in-kind deliveries:
In attempting to arrive at a 'uniform' definition of an IKD on the basis of ESA's experience to date in this domain, it might be identified as:
"Goods transferred or services rendered to the Agency by a Member State and falling within an agreed programme content, not being funded by means of Article XIII of the Convention, but contributed by the Participating State free of charge to the Agency for the purpose of the programme in question".
In order to identify issues associated with such a method of participating in ESA programmes, and analyse its impact on the Agency's framework and management practices, this definition has to be measured against the basic assumptions and elements of the Agency's system vis-a-vis the following points :
There is an obvious difference here which cannot be avoided by any ESA internal decision or text approved by Delegations of Member States. However, a new Optional Programme containing in-kind deliveries should be transparent and have the same character as other ordinary commitments towards ESA Programmes. To achieve this, the IKD needs to be defined and included already at the Programme Proposal stage and subsequently inscribed clearly in the Enabling Resolution approving the Programme and in the Declaration constituting the multilateral agreement between Participating States. The modalities of its execution need to be set in the Implementing Rules, thus implying the conclusion of a government-level agreement between ESA and the State concerned. Any IKD proposed by a Participant after the entry into force of the Declaration and not yet included in the work content would require an addition to the Programme content and also some adaptations to the Implementing Rules. Most of these decisions will have to be taken by unanimous vote of the Participating States. However, not all of the legal risks explained above may be avoided with such an alternative solution.
IKDs could be regarded as a way of fulfilling programme content without fully subscribing to the financial envelope. This has the indirect effect of creating structural deficits within the envelope, by diverting financial resources out of the programme envelope towards national investments. Such a solution has the disadvantage of leaving the Agency with the problem of managing an incompletely financed programme and also avoiding the normal allowance of a cost-overrun margin for the investment in question. The different obligations of States are also obvious here. Whatever the attitude taken by the national investment covering the IKD, there is still the risk of a cost overrun with the IKD and, because of their mutual interest in the total programme's success, in fine all of the other Participating States might end up bearing the additional cost to complete the programme.
In order to avoid this situation, a clear-cut separation has to be made between IKDs and the overall financial envelope: the ESA financial envelope should only contain funding for internal costs plus ESA-initiated industrial contracts. Such an envelope will then be 100% financed without any deficit, and the usual 120% rule can then easily be applied for its original purpose. IKD elements would have to be announced and committed to in the same Declaration and Financial Annex, but on a separate basis, outside the ESA financial envelope. Cost overruns on IKDs would then be solely the responsibility of the providing entity. An efficient project would need to keep full control of the programme content entrusted to it, with full management authority for each of the elements composing it. This would minimise, although not eliminate, the cost overrun risk for the programme.
The debate to date within ESA has shown that several Delegations refuse to accept solidarity towards this kind of programmatic risk, seeing the desirable solution in the case of a Participating State's non-compliance with its responsibility to deliver in time as a corresponding obligation to provide alternatives to the programme. These 'alternatives' would need to be fully understood and accepted by the other Participants, thereby causing some delay in the decision-making process. In any case, this solution does not complete the programme as planned and may cause disappointments and cost increases for the other participants.
As the price tag of each IKD activity will have to be known at the start of the programme, the ESA charging policy for internal costs could be applied, so that the general overheads need not increase substantially. This has already been done in the case of Artes-9, the programme currently most affected by the IKD concept.
For the future, therefore, special criteria need to be considered for insertion into the Financial Regulations to cover this point. Such criteria might allow various rate levels to be applied, depending on the return of the development work, service or other activity. The cost of reproduction or the recurrent price of the IKD should form the basis for the calculation. Also, for such activities which can be likened in a way to external customer activities, a handling charge has to be levied as a fair percentage so as not to favour this approach unduly, and not to encourage such a regime compared with the classical method of contributing to the Agency's programmes. The 'income' from this handling charge because of the programme management cost involved, may appropriately be credited to the Programme concerned and not to the General Budget as in the case of external customers.
The situation could be clarified if, at the start of a programme, Participating States clearly and unanimously separate and define what is to be managed by ESA and what is not. Activities not managed by ESA would remain outside the Agency's programmes and responsibility as regards industrial- policy considerations. All IKDs should be evaluated against the industrial return of the country offering them: IKDs counted as part of the industrial return of a country would have the effect of increasing the industrial work foreseen for that country. If on the other hand, IKDs were to be omitted from industrial-return statistics, they would be carried out over and above the 'normal' share of work that should go to that country. Clearly, this would provide an incentive to offer more and more IKDs, either to have critical work done at home, or to move the project in the direction sought by the donor country, or simply as a means of avoiding competition.
The 'contribution-in-kind' may be the result of a national item (intellectual property, knowhow/design, software or hardware) that has already been developed or partially developed. In such a case it is likely to figure in the industrial development as 'Agency-furnished equipment' and the Agency takes responsibility for any technical shortfall, inadequacy or lateness. The firm concerned will try to avoid responsibility in its contract with the contributing State, and will have sufficient ammunition to do so (including externally imposed interfaces).
If the contribution is only financial, then a contract will have to be placed with the firm identified, and this will presumably involve development. The only way that the programme can maintain its technical and programmatic integrity is to incorporate the work within the prime contract, subject to both the technical and managerial controls of the ESA Project Manager and the Prime Contractor, and the ESA contract conditions, despite national and industrial resistance to this control.
Several of these problems can be solved by drafting appropriate contractual terms, but it would be necessary to:
This will probably involve an interlocking series of agreements, and care will have to be taken that all cross- links between the parties are complete. If there are any gaps, then it will almost certainly be the Agency which bears the risks, consequences and subsequent costs. The situation may be aggravated by differences in applicable laws in the countries concerned.
In conclusion, there is no reason to reject the IKD principle as such, but some work still needs to be done within the Agency to accommodate these innovative methods of contributing to ESA Programmes. However, we have to recognise the complexity and the exceptional nature of the approach. The debate now in progress, and also the Council Resolution at Ministerial Level, recognises the need to establish Agency- wide guidelines for the future for IKDs. In order to be incorporated sensibly into the Agency's programmes on a realistic scale, IKDs will need to:
On the basis of this analysis, it might be prudent to introduce into the Agency's legal framework some ground rules, guidelines or code-of-conduct commensurate with the above- defined issues associated with in-kind deliveries. The objective would be to have these guidelines approved by the Member States to govern all ESA Programmes in such cases and then used as a reference when drafting legal texts such as Resolutions, Declarations and Implementing Rules (completed by detailed financial provisions), therefore allowing greater security, transparency and flexibility in each new Optional Programme.